CE/CON/SUR/FLS/2025/01 |
|
Name of the
Work |
Conducting Final Location Survey (FLS) for (i) New BG Railway Line Projects (900.00km) & (ii) Gauge Conversion / Doubling / Third Line / 3rd & 4th line (600.00km) of various projects in India, Nepal and Bangladesh with Geo-Technical Investigation, preparing EIRR, EPC document & submission of DPR etc. as per Railway Board's latest guide lines complete in all respect. |
|
Corrigendum
No. |
02 |
|
Corrigendum
Date |
30/7/2025 |
|
Corrigendum
Description |
1. Completion Period changed from 12 Months to 36 Months.
2. Pre-Bid Reply submitted.
|
|
|
|
|
|
|
|
|
|
|