Welcome, Guest |
|
|
|
|
Corrigendum Details |
|
|
|
ID |
|
|
Tender No. |
CE/CON/SUR/FLS/2025/01 |
|
Name of the
Work |
Conducting Final Location Survey (FLS) for (i) New BG Railway Line Projects (900.00km) & (ii) Gauge Conversion / Doubling / Third Line / 3rd & 4th line (600.00km) of various projects in India, Nepal and Bangladesh with Geo-Technical Investigation, preparing EIRR, EPC document & submission of DPR etc. as per Railway Board's latest guide lines complete in all respect. |
|
Corrigendum
No. |
01 |
|
Corrigendum
Date |
29/7/2025 |
|
Corrigendum
Description |
1. Tender Closing Date modified from 13-08-2025 14:30 Hrs to 22-08-2025 14:30 Hrs.
2. Bidding start date modified from 30-07-2025 to 08-08-2025
|
|
|
|
|
|
|
|
|
|
|