NAME OF PROJECT :New line from New Maynaguri to Jogighopa

 

 

1.

 Year of sanction

:

2000-01  

2.

Cost of project

:

Rs.1022.12 Crores.

3.

Length

:

257 Km

4.

State Served

:

West Bengal  and Assam

5.

Month of CCEA approval

 

2/2000

6.

Scope of major works: (excluding Golokganj-Gauripur section)

 

 

 

Earthwork

 

141.35 Lac Cum

 

Major Bridge

 

58 Nos

 

Minor Bridge

 

292 Nos

 

ROB/RUB

 

103 Nos

 

Tunnel

 

Nil

  Ballast   6.77 Lac cum
  Track linking   265.74
  Important bridge   1 (over river Gangadhar)
 