Progress of Works upto  Oct 2008

                              System Map                             Project and survey Map                              

 

*-Item completed

 

Name of the project

Anticipated cost/ Up-to-date Expenditure (in Cr)

Target

Progress (up-to-date)

Earthwork (lac cum)

Major Bridge (nos)

Minor Bridge(nos)

ROB/ RUB (nos)

Tunnel in Mtrs

Ballast (Lac Cum)

Track linking (km)

Others

% progress

1

Kumarghat-Agartala new line project (BG) (National Project)

879.99

 

248

15

182

26

4872

2.0

109

 

 

 

Progress

893.19

 

248 *

15 *

182*

26*

4872

1.91

109

 

100

Kumarghat-Manu commissioned in 2002. Manu –Agartala commissioned on 05.10.08.

2

Rail cum road Bridge over river Brahmaputra at Bogibeel with linking lines  (National Project)

1767.36

 

296.73

19

98

15

 

2.46

89.74

Main Bridge-1

 

 

Progress

1084.34

Mar 2012

189.69

13

88

10

 

1.14

35.90

 

61.35

Work for link lines and sub-structure of Main bridge in progress.

3

Jiribam-Imphal (Tupul)    (National Project)

727.56

 

250

35

287

6

17250

165000

97.9

 

 

 

Progress

39.02

Mar 2012

29

0

5

0

0

0

0

 

6.20

4

New BG line from Azara to Byrnihat (National Project)

200

 

 

 

 

 

 

 

 

 

 

 

Progress

0.10

Mar’2013

 

 

 

 

 

 

 

 

 0.50

5

New line from Dimapur to Kohima (Zubza) (National Project)

850

 

 

 

 

 

 

 

 

 

 

 

Progress

0

Mar’2013

 

 

 

 

 

 

 

 

 

6

New BG line from Agartala to Sabroom

813.34

 

 

 

 

 

 

 

 

 

 

 

Progress

0

 Mar’2013

 

 

 

 

 

 

 

 

 

7

New BG line from Bhairabi to Sairang

619.34

 

 

 

 

 

 

 

 

 

 

 

Progress

0

 Mar’2013

 

 

 

 

 

 

 

 

 

 8

New BG line from New Maynaguri to Jogighopa

1022.12

 

157.85

58

304

105

 

6.77

265.74

Important bridge-1

 

 

Progress

245.90

Mar 2012

38.30

10

105

9

 

 

 

 

24.06

9

Harmuti-Itanagar

160.48

 

 

 

 

 

 

 

 

 

 

 

Progress

15.10

Mar2011

 

 

 

 

 

 

 

 

 

10

New BG line from Eklakhi to Balurghat and Gazole to Itahar

285.93

 

 

 

 

 

 

 

 

 

 

 

Progress

221.34

Mar2010

 

 

 

 

 

 

 

 

77.68

Eklakhi-Balurghat commissioned on 30.12.2004

 11

Dudhnoi to Depa (Mendipathar)

86.22

 

 

 

 

 

 

 

 

 

 

 

Progress

0.51

Mar’2013

 

 

 

 

 

 

 

 

 

12

New BG line from Araria to Galgalia (Thakurganj)

300

 

 

 

 

 

 

 

 

 

 

 

Progress

0.50

Mar’2011

 

 

 

 

 

 

 

 

0.30

13

New BG line from Kishanganj to Jalalgarh

282.92

 

 

 

 

 

 

 

 

 

 

 

 

 

 Mar’2014

 

 

 

 

 

 

 

 

 

 

  NEXT