Scope of Works

 

NAME OF PROJECT : Gauge Conversion of Katakhal Jn. to Bhairabi Section.

 

1.

Year of sanction

:

1998 - 1999

2.

Cost of project

:

Rs. 88.70 Crs.

3.

Length

:

84.00 Km

4.

State Served

:

Assam, Mizoram

5.

Month of CCEA approval

:

 

6.

Scope of major works:

 

 

 

Earthwork

 

14.40 Lac cum

 

Major Bridge

 

16 Nos.

 

Minor Bridge

 

170 Nos

 

ROB/RUB

 

NIL 

 

Tunnel

 

NIL

 

Ballast

 

1.15 Lac cum

 

Track linking

 

84.50

 

 

 

 

 