NAME OF PROJECT
: Gauge Conversion of NJP-NBQ section
including branch line.
|
|
|
|
1. |
Year of
sanction |
: |
1997 - 1998
|
|
2. |
Cost of project
|
: |
Rs. 960.48 Crs.
|
|
3. |
Length
|
: |
417.00 Km
|
|
4. |
State Served
|
: |
West Bengal,
Assam. |
|
5. |
Month of CCEA
approval |
: |
2/1999 |
|
6. |
Scope of major
works:
(For Branch
line-Fakiragram-Dhubri and Golakganj- Gauripur sections) |
|
|
Earthwork
|
|
6.10 Lac Cum
|
|
|
Major Bridge
|
|
15Nos.
|
|
|
Minor Bridge
|
|
27 Nos.
|
|
|
ROB/RUB
|
|
NIL |
|
|
Tunnel
|
|
NIL
|
|
|
Ballast |
|
1.42 Lac cum |
|
|
Track linking |
|
66 kms. |
|
|
|
|