NAME OF PROJECT : Gauge Conversion of NJP-NBQ section including branch line.

 

1.

 Year of sanction

:

1997 - 1998

2.

Cost of project

:

Rs. 960.48 Crs.

3.

Length

:

 417.00 Km

4.

State Served

:

West Bengal, Assam.

5.

Month of CCEA approval

:

2/1999

6.

Scope of major works:

(For Branch line-Fakiragram-Dhubri and Golakganj- Gauripur sections)

 

Earthwork

 

6.10 Lac Cum

 

Major Bridge

 

15Nos.

 

Minor Bridge

 

27 Nos.

 

ROB/RUB

 

NIL

 

Tunnel

 

NIL

 

Ballast

 

1.42 Lac cum

 

Track linking

 

66 kms.