Scope of Works

NAME OF PROJECT : Lumding-Silchar Gauge Conversion including Silchar-Jiribam , Badarpur-Baraigram and Baraigram-Kumarghat.

 

1.

 Year of sanction

:

1996-97

2.

Cost of project

:

Rs. 1676.71 Crs.

3.

Length

:

367.79  Kms

4.

State Served

:

Assam , Manipur & Tripura

5.

Month of CCEA approval

 

7/1996

6.

Scope of major works:

 

 

 

Earthwork

 

629.90 Lac Cum

 

Major Bridge

 

130 Nos.

 

Minor Bridge

 

657 Nos.

 

ROB/RUB

 

9 Nos

 

Tunnel

 

10748 mts

 

Ballast

 

8.96 Lac cum

 

Track linking

 

379 kms

 
 