Scope of Works
NAME OF PROJECT : Lumding-Silchar Gauge Conversion including Silchar-Jiribam , Badarpur-Baraigram and Baraigram-Kumarghat.
1.
Year of sanction
:
1996-97
2.
Cost of project
Rs. 1676.71 Crs.
3.
Length
367.79 Kms
4.
State Served
Assam , Manipur & Tripura
5.
Month of CCEA approval
7/1996
6.
Scope of major works:
Earthwork
629.90 Lac Cum
Major Bridge
130 Nos.
Minor Bridge
657 Nos.
ROB/RUB
9 Nos
Tunnel
10748 mts
Ballast
8.96 Lac cum
Track linking
379 kms
<<Previous Next>>
New Line
Gauge conversion
14
15
21