| PROGRESS OF WORKS UPTO MAY 2009 | ||||||||||||
| SN | Name of the project |
Anticipated cost / Up-to-date Expenditure (in Cr) |
Target | Progress (up-to-date) | ||||||||
| Earthwork (lac cum) | Major Bridge (nos) | Minor Bridge (nos) | ROB/ RUB (nos) | Tunnel in Mtrs | Ballast (Lac Cum) | Track linking (km) | Others | % progress | ||||
| 1 | Rail cum road Bridge over river Brahmaputra at Bogibeel with linking lines (National Project) | 3087.44 | Mar 2012 | 296.73 | 19 | 98 | 15 | 2.84 | 85.86 | Main Bridge-1 | ||
| Progress | 1391.71 | 246.53 | 13 | 90 | 12 | 1.92 | 67.25 | 28.93 | ||||
| Work for link lines and sub-structure of Main bridge in progress. | ||||||||||||
| 2 |
Jiribam-Imphal (Tupul) (National Project) |
2492.53 |
Mar 2012 for Jiribam-Imphal |
237.5 | 19 | 65 | 9 | 16738 | 1.65 | 97.9 | ||
| Progress | 73.63 | 60.48 | 0 | 12 | 0 | 0 | 0 | 0 | 3.67 | |||
| 3 | New BG line from Azara to Byrnihat (National Project) | 200 | Not fixed | |||||||||
| Progress | 0.34 | 0.08 | ||||||||||
| 4 |
New line from Dimapur to Kohima (Zubza) (National Project) |
850 | Mar 2013(T) | |||||||||
| Progress | 0.83 | |||||||||||
| 5 | New BG line from Agartala to Sabroom ( upto Udaipur only) | 813.34 | Mar 2014 ( T) | 67.32 | 9 | 42 | 26 | 0.11 | 44.11 | |||
| Progress | 1.14 | |||||||||||
| 6 | New BG line from Bhairabi to Sairang | 619.34 | Mar 2014 (T) | |||||||||
| Progress | 0 | |||||||||||
| 7 | New BG line from New Maynaguri to Jogighopa | 1480.71 | 157.85 | 58 | 304 | 105 | 6.77 | 265.7 | Important bridge-1 | |||
| Progress | 245.9 | Not fixed | 59.08 | 36 | 83 | 40 | 24.1 | |||||
| 8 | Harmuti-Itanagar | 160.48 | 40 | 20 | 33 | 2 | 0.6 | 21 | ||||
| Progress | 15.1 | Mar-12 | 5.40 | 2 | 5 | |||||||
| 9 | New BG line from Eklakhi to Balurghat and Gazole to Itahar | 285.93 | ||||||||||
| Progress | 221.34 | Not fixed | 77.7 | |||||||||
| Eklakhi-Balurghat commissioned on 30.12.2004 | ||||||||||||
| 10 | Dudhnoi to Depa (Mendipathar)0.30 | 86.22 | 17.40 | 1 | 40 | 10 | 0. 420 | 18 | ||||
| Progress | 0.51 | Mar’2013 | 0.30 | 5 | ||||||||
| 11 | New BG line from Araria to Galgalia (Thakurganj) | 300 | ||||||||||
| Progress | 0.5 | Not fixed | 0.3 | |||||||||
| 12 | New BG line from Kishanganj to Jalalgarh | 282.92 | ||||||||||
| Progress | Not fixed | |||||||||||
| 13 | New BG line from Sevok - Rangpo | 1339.42 | Not fixed | |||||||||
| Progress | ||||||||||||