NAME OF PROJECT : Kumarghat-Agartala new line project (BG)
National Project
System Map
SALIENT FEATURES:
1.
Year of sanction
:
1996-97
2.
Cost of project
Rs.879.99 Crores.
3.
Length
109 Km
4.
State Served
Tripura
5.
Month of CCEA approval
07/1996
Scope of major works:
Earthwork
248 Lac Cum
Major Bridge
15 Nos
Minor Bridge
182 Nos
ROB/RUB
26 Nos
Tunnel
3 Nos (4872m)
New Line
Gauge conversion
14
15
21